Please use the grid provided on page two of the Candidate Answer Booklet to record your answers to each multiple  choice question. Do not write out the answers to the MCQs on the lined pages of the answer booklet.
Each question is worth 2 marks.

Which of the following statements are correct?
(1) The sensitivity of a project variable can be calculated by dividing the project net present value by the present value of the cash flows relating to that project variable
(2) The expected net present value is the value expected to occur if an investment project with several possible outcomes is undertaken once
(3) The discounted payback period is the time taken for the cumulative net present value to change from negative to positive
A 1 and 2 only
B 1 and 3 only
C 2 and 3 only
D 1, 2 and 3

Answer:

B

ACCA特许公认会计师F段+OBU本科学位班【签约班】

高级商业会计证书+英国牛津布鲁克斯大学学士学位 不过重读1年

查看折扣

ACCA特许公认会计师P段【签约班】

名师授课,签约过关有保障!不过免费重读1年

查看折扣

ACCA特许公认会计师全科【签约班】

名师授课,助您零基础直达ACCA初级

查看折扣

更多精彩:

ACCA会员权利 & 义务知多少

ACCA学历项目:英国伦敦大学专业会计硕士(UOL)学位申请

ACCA会员分享 | 会计人成长重在“宽度”与“高度”